Martin® Belt Cleaners Reduce Carryback by 78%
A large fracking sand plant in Texas with 5MM TPY capacity was experiencing serious carryback issues on its main conveyor, with wet sand clinging to the belt. The material would either transfer to the bend pulley, fall to the ground or fall into the take-up pulley where it would damage the belt. Cleanup was needed almost every day, at times becoming so bad that the process would have to be shut down for maintenance.
Mr. Blade Program Delivers Solution to Carryback Problem
The new Mr. Blade program from Martin Engineering assures customers of professionally installed replacement blades that are matched to their specific operating conditions for optimum cleaning performance and service life. Image Materials benefits from a consistent supply of freshly-molded, high-quality blades delivered directly from the factory and installed by a trained service technician.